if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

(1 point) A hot air balloon is launched from the ocean beach. As it moves inland, it rises and then falls, having a path given by p(x)= - 2x^2/2500 +0.7x where
Ava buys 3.5 pounds of strawberries for $2.99 per pound. How much does she spend?
write your own poem and illustrate. You must TELL the kind of poem that it is at the bottom of the page - and WHY it is that type of poem (couplet, quatrain, ha
royalred just started production of a new synthetic motor oil they have overhead costs of $21,804.00 a month plus manufacturing costs of $4.99 per quart of oil
FIND THE MISSING LENGTH.
pls pls pls pls pls pls pls
At 2:00 PM the temperature is 18°F. At 10:00 PM the temperature is -9°F. What is the change in temperature from 2:00 PM to 10:00 PM?​
How did the Oklahoma enabling act impact Sequoyah?
What is the perimeter of the pentagon below? 3.2 cm?​
What is -4x^2-6x-4 in vertex form?