15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Many soldiers who fought in the battle of antietam saw it as a defeat for both armies. why
How did the korean war change the way korea was divided?
Under which circumstance might you receive a tax refund from the IRS?
Calculate how much the insurance company would pay in benefits in the following case. John has purchased collision insurance with a $100-deductible clause, an
What is medical sociology
which of the following terms describes the object below?check all that applyA.prismB.solidC.cubeD.pyramidE.polyhedronF.polygon
A basketball player gets 2 free-throw shots when she is fouled by a player on the opposing team. She misses the first shot 40% of the time. When she misses the
Homogamy, a term sociologists use to mean the tendency to choose romantic partners based on similarities in background and group membership, is very common. Why
A gardener plants 200 flowering plants of the same species. 98 plants have white (v) flowers and the remaining have violet (V) flowers. What must be the allelic
Why do scientists think that our solar system must have formed sometime after nearby supernovae explosions?