Which field can be used to track the progress on tasks that a user has created?
Subject
Start Date
Due Date
% Complete
Help plz

Respuesta :

elitrad
elitrad elitrad
  • 03-07-2020

Answer:

% complete

Explanation:

% complete tracks progress (how far done you are, aka completion)

Answer Link
deliaaaxox deliaaaxox
  • 07-07-2020
Percent complete will be used to track progress on task that the user has created :))
Answer Link

Otras preguntas

This statement is objective: 6:30 a. m. is far too early for school to start. true or false
how can you reduce the stress of completing a project
Why did early Americans write the Constitution and Bill of Rights? They wanted to convince Great Britain to let them have independence without further fighting.
In 1824, Mexico became a monarchy a republic a autocracy a communist state
According to the Declaration of Independence, what are the three most basic rights? freedom of speech, assembly, and religion the right to vote, to bear arms, a
The end of the war in Europe compared to the end of the war in the Pacific
How did the end of the slave trade in 1808 help draw African Americans to Christian churches
What is one reason there were few Dutch immigrants in the Middle Colonies before 1800? Select the best answer from the choices provided. 1.The number of German
solve for x 4^x-2=256
Nature of the predicate